I-405 Carpool Lane I-10 to US 101 (Northbound)

Description: In Los Angeles from Route 10 to Route 101. Construct one HOV Lane Northbound on Route 405 from Route 10 to Route 101. (TCRP #39)

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles
City Los Angeles
Zip Code 90025, 90034, 90049, 90064, 90066, 90077, 91403
 
Senate District
23, 28
Assembly District 42, 47
Congressional District 28, 30, 36
 
Caltrans District
07
 
 
County/State Route Los Angeles 405
Postmile Begin/End 28.8 39
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)  22929      
Lane Miles Added (HOV)  10.2      
Peak Period Time Savings (minutes)  1673840      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Department of Transportation Greg Farr (818) 254-5439   greg.farr@dot.ca.gov
Design (PS&E) Phase
Department of Transportation Greg Farr (818) 254-5439   greg.farr@dot.ca.gov
Right of Way Phase
Department of Transportation Greg Farr (818) 254-5439   greg.farr@dot.ca.gov
Construction Phase
Department of Transportation Mark Miller 213-922-7289   millerm@metro.net
 
Corridor System Management Plan
Department of Transportation Greg Farr (818) 254-5439   greg.farr@dot.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
CMIA
$730,000 $0 $730,000
Non-bond Funding
State/Federal*
$90,000 $100,000 $190,000
Local**
$130,000 $87,700 $217,700
Non Budgeted ETC
$0 $0 $0
 
Total**** $950,000 $187,700 $1,137,700

**** Totals may not add up exactly to column amounts due to rounding

# Approved is planned budget

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$15,000 $7,000 $22,000 $21,016
Design(PS&E)
$60,000 $-21,000 $39,000 $27,035
Right of Way
$97,000 $0 $97,000 $66,072
Construction
$778,000 $201,700 $979,700 $925,288
 
Total* $950,000 $187,700 $1,137,700 $935,705

* Totals may not add up exactly to column amounts due to rounding

** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
07/01/2001 

07/01/2007 
 

 
07/02/2001 

02/29/2008 
100  07/02/2001 

02/29/2008 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/01/2007 

05/01/2011 
 

 
01/01/2007 

10/10/2008 
100  01/01/2007 

10/10/2008 


Begin Right of Way Phase

End Right of Way Phase
01/01/2008 

03/01/2011 
 

 
12/29/2014 

09/18/2012 
92  12/29/2014 

09/18/2012 


Begin Construction Phase

End Construction Phase
04/01/2009 

04/01/2013 
 

 
04/23/2009 

03/01/2017 
04/23/2009 

02/19/2020 


-36 
Begin Closeout Phase

End Closeout Phase
12/01/2013 

12/01/2014 
 

 
03/01/2017 

06/10/2021 
10/21/2019 

06/10/2021 
-32 

Corridor System Management Plan
Adoption Date 06/01/2009    06/01/2009   
Implementation Date 07/01/2009    07/01/2009   
????????
Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 22929
Lane Miles Added (HOV) 10.2
Peak Period Time Savings (minutes) 1673840

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.