I-405 Carpool Lane I-10 to US 101 (Northbound) |
Description: In Los Angeles from Route 10 to Route 101. Construct one HOV Lane Northbound on Route 405 from Route 10 to Route 101. (TCRP #39)
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Los Angeles |
City | Los Angeles |
Zip Code | 90025, 90034, 90049, 90064, 90066, 90077, 91403 |
Senate District |
23, 28 |
Assembly District | 42, 47 |
Congressional District | 28, 30, 36 |
Caltrans District |
07 |
County/State Route | Los Angeles 405 |
Postmile Begin/End | 28.8 39 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 22929 | |
Lane Miles Added (HOV) | 10.2 | |
Peak Period Time Savings (minutes) | 1673840 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Department of Transportation | Greg Farr | (818) 254-5439 | greg.farr@dot.ca.gov | |
Design (PS&E) Phase |
Department of Transportation | Greg Farr | (818) 254-5439 | greg.farr@dot.ca.gov | |
Right of Way Phase |
Department of Transportation | Greg Farr | (818) 254-5439 | greg.farr@dot.ca.gov | |
Construction Phase |
Department of Transportation | Mark Miller | 213-922-7289 | millerm@metro.net | |
Corridor System Management Plan |
Department of Transportation | Greg Farr | (818) 254-5439 | greg.farr@dot.ca.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
CMIA |
$730,000 | $0 | $730,000 | ||||
Non-bond Funding | |||||||
State/Federal* |
$90,000 | $100,000 | $190,000 | ||||
Local** |
$130,000 | $87,700 | $217,700 | ||||
Non Budgeted ETC |
$0 | $0 | $0 | ||||
Total**** | $950,000 | $187,700 | $1,137,700 |
**** Totals may not add up exactly to column amounts due to rounding
# Approved is planned budget
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
||||
Environmental |
$15,000 | $7,000 | $22,000 | $21,016 | |||
Design(PS&E) |
$60,000 | $-21,000 | $39,000 | $27,035 | |||
Right of Way |
$97,000 | $0 | $97,000 | $66,072 | |||
Construction |
$778,000 | $201,700 | $979,700 | $925,288 | |||
Total* | $950,000 | $187,700 | $1,137,700 | $935,705 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.
Project Schedule Baseline Summary | |||||||
---|---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
|
Begin Environmental Phase
End Environmental Phase |
07/01/2001 07/01/2007 |
|
07/02/2001 02/29/2008 |
100 | 07/02/2001 02/29/2008 |
0 0 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
01/01/2007 05/01/2011 |
|
01/01/2007 10/10/2008 |
100 | 01/01/2007 10/10/2008 |
0 0 |
|
Begin Right of Way Phase
End Right of Way Phase |
01/01/2008 03/01/2011 |
|
12/29/2014 09/18/2012 |
92 | 12/29/2014 09/18/2012 |
0 0 |
|
Begin Construction Phase
End Construction Phase |
04/01/2009 04/01/2013 |
|
04/23/2009 03/01/2017 |
0 | 04/23/2009 02/19/2020 |
0 -36 |
|
Begin Closeout Phase
End Closeout Phase |
12/01/2013 12/01/2014 |
|
03/01/2017 06/10/2021 |
0 | 10/21/2019 06/10/2021 |
-32 0 |
|
Corridor System Management Plan |
|||||||
Adoption Date | 06/01/2009 | 06/01/2009 | 0 | 0 | |||
Implementation Date | 07/01/2009 | 07/01/2009 | 0 | 0 |
????????
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 22929 | |
Lane Miles Added (HOV) | 10.2 | |
Peak Period Time Savings (minutes) | 1673840 |
Bond Funding Cost | |
---|---|
Adopted: |
|
Current Approved: |
|
Actual Expenditures: |
Status as of December 31, 2023.